當(dāng)前位置: 首頁 > 節(jié)能環(huán)保 > 垃圾發(fā)電

華星東方承建的四川省巴中市垃圾焚燒發(fā)電項(xiàng)目二期煙氣凈化工程通過竣工驗(yàn)收

中國電力網(wǎng)發(fā)布時(shí)間:2022-06-01 08:48:57

華星東方公司承建的四川省巴中市垃圾焚燒發(fā)電項(xiàng)目二期煙氣凈化工程于2022年5月15日通過竣工驗(yàn)收。

The flue gas cleaning (FGC) project for Bazhong waste-to-energy plant Phase II undertaken by Huaxing East passed the completion acceptance on May 15, 2022.

該項(xiàng)目一期工程已建成投運(yùn)。本期為二期工程,擬建設(shè)規(guī)模為日處理生活垃圾600噸,配置1臺(tái)600t/d機(jī)械爐排爐和1臺(tái)15MW凝汽式汽輪發(fā)電機(jī)組。煙氣處理采用SNCR+旋轉(zhuǎn)噴霧半干法+干法消石灰噴射+活性炭噴射+布袋除塵器+飛灰輸送、儲(chǔ)存及穩(wěn)定化工藝,為我司EPC工程。

The Phase I of the plant has been completed and put into operation. Phase II of the plant will construct a 600 t/d mechanical grate and a 15 MW condensing steam turbine. The FGC will apply SNCR + rotary spray semi-dry + slaked lime injection dry + activated carbon injection + bag filter + fly ash conveying, storage and stabilization process. It is an EPC project of Huaxing East.

華星東方在四川省的業(yè)績涵蓋包括:鄧雙、金堂、隆豐、資陽、巴中、廣元、宣漢、自貢、中江、廣安、宜賓等多個(gè)項(xiàng)目。

Huaxing East's achievements in SiChuanProvince include: Dengshuang,Jintang,Longfeng,Ziyang,Bazhong,Guangyuan,Xuanhan,Zigong,Zhongjiang,GuangAn,Yibinetc.